Co located generation × Interconnection queue

Co-located generation is the engineering response to interconnection queue length. Posts 010, 017, and 022 all document the principle, with Post 022 quantifying the Texas-specific scale of the queue that co-location bypasses.

Entries

3 citing both topics
04.19

ERCOT Queue Hits 410 GW of Large Load Requests

Texas interconnection queue now tracks 410 GW of large-load requests, 87% from data centers, a 4.7x multiple of current peak demand. SB-6 rulemaking will determine whether projects connect to the grid or self-generate behind-the-meter.

04.09

Microsoft-Chevron $7B Texas Gas Plant

Microsoft and Chevron announced a $7 billion exclusive deal to build a dedicated 2,500 MW natural gas power plant near Pecos, Texas, marking the first time an oil supermajor is developing infrastructure directly for a tech hyperscaler's AI operations.

04.09

Behind-the-Meter Gas Generation Acceleration

Behind-the-meter gas generation for data centers accelerated to 56 GW across 46 projects in 2025, tripling new facility proposals and shortening project timelines to 3 years versus 5+ years for grid interconnection. The trend may break the 2002 record for annual gas power additions.

← Map
Map Pairing 3 entries

Co located generation × Interconnection queue

Co-located generation is the engineering response to interconnection queue length. Posts 010, 017, and 022 all document the principle, with Post 022 quantifying the Texas-specific scale of the queue that co-location bypasses.

04.19

ERCOT Queue Hits 410 GW of Large Load Requests

Texas interconnection queue now tracks 410 GW of large-load requests, 87% from data centers, a 4.7x multiple of current peak demand. SB-6 rulemaking will determine whether projects connect to the grid or self-generate behind-the-meter.

04.09

Microsoft-Chevron $7B Texas Gas Plant

Microsoft and Chevron announced a $7 billion exclusive deal to build a dedicated 2,500 MW natural gas power plant near Pecos, Texas, marking the first time an oil supermajor is developing infrastructure directly for a tech hyperscaler's AI operations.

04.09

Behind-the-Meter Gas Generation Acceleration

Behind-the-meter gas generation for data centers accelerated to 56 GW across 46 projects in 2025, tripling new facility proposals and shortening project timelines to 3 years versus 5+ years for grid interconnection. The trend may break the 2002 record for annual gas power additions.