Map Pairing Cited together in 3 entries

Gas turbine lead time × Co located generation

The eight-year turbine lead time is what pushes hyperscalers toward co-location with developers who already hold slots. Posts 002, 005, and 010 document the substitution: when a utility cannot deliver, a co-located developer with a reserved slot can.

Entries

3 citing both topics
04.09

Behind-the-Meter Gas Generation Acceleration

Behind-the-meter gas generation for data centers accelerated to 56 GW across 46 projects in 2025, tripling new facility proposals and shortening project timelines to 3 years versus 5+ years for grid interconnection. The trend may break the 2002 record for annual gas power additions.

04.05

Gas Turbine Supply Crunch

Three major gas turbine OEMs face record backlogs and lead times stretching to 8 years, with manufacturing capacity now the binding constraint on grid and data center deployments. Combined cycle systems dominate 70 percent market share, while slot reservations become strategic assets.

04.05

Behind-the-Meter Gas Generation for Data Centers

Behind-the-meter gas generation now powers 48 GW, roughly a third of all planned US data center capacity. Williams, Bloom Energy, and hyperscalers including Google and Meta are building modular gas plants that deploy in months, sidestepping years-long grid interconnection delays to meet AI's power appetite.

← Map
Map Pairing 3 entries

Gas turbine lead time × Co located generation

The eight-year turbine lead time is what pushes hyperscalers toward co-location with developers who already hold slots. Posts 002, 005, and 010 document the substitution: when a utility cannot deliver, a co-located developer with a reserved slot can.

04.09

Behind-the-Meter Gas Generation Acceleration

Behind-the-meter gas generation for data centers accelerated to 56 GW across 46 projects in 2025, tripling new facility proposals and shortening project timelines to 3 years versus 5+ years for grid interconnection. The trend may break the 2002 record for annual gas power additions.

04.05

Gas Turbine Supply Crunch

Three major gas turbine OEMs face record backlogs and lead times stretching to 8 years, with manufacturing capacity now the binding constraint on grid and data center deployments. Combined cycle systems dominate 70 percent market share, while slot reservations become strategic assets.

04.05

Behind-the-Meter Gas Generation for Data Centers

Behind-the-meter gas generation now powers 48 GW, roughly a third of all planned US data center capacity. Williams, Bloom Energy, and hyperscalers including Google and Meta are building modular gas plants that deploy in months, sidestepping years-long grid interconnection delays to meet AI's power appetite.