Map Pairing Cited together in 4 entries

Oem backlog × Hyperscaler capex

OEM backlog and hyperscaler capex are joined at the source. Post 067 documents the Siemens Energy CFO commentary attributing US demand explicitly to data centers, the clearest OEM-side acknowledgment of the hyperscaler-OEM coupling.

Entries

4 citing both topics
05.25

Siemens Energy Q2 FY26: €154B Backlog, Guidance Raised

Siemens Energy's Q2 FY2026 print on May 12 booked another €17.7B in all-time-record orders, with Gas Services alone delivering €8.9B and 77 turbine orders (12 GW). Order backlog reached €154B; FY26 guidance was raised to 14-16% revenue growth and ~€4B net income.

05.25

Hyperscaler Q1 2026 Capex: From $630B to $725B in One Quarter

The four hyperscalers reported Q1 2026 on April 29 and collectively raised 2026 capex guidance from the pre-quarter $630B figure to roughly $725B - up 77% from 2025's $410B. Microsoft alone now plans $190B, with $25B of that attributed to memory chip and component costs.

05.25

GE Vernova Q1 2026: Backlog Hits 100 GW, Orders +71%

GE Vernova's Q1 2026 print on April 22 turned the pre-guide into audited numbers: gas turbine backlog jumped from 83 GW to 100 GW in a single quarter, total backlog hit $163B, and the company pulled its $200B backlog target forward from 2028 to 2027. Pricing is rising faster than inflation.

05.25

The Order Book Hits the Tape

The AI power buildout has moved from forecast to order book. The richest companies in the world are prepared to spend almost without limit. They have discovered that money cannot manufacture time.

← Map
Map Pairing 4 entries

Oem backlog × Hyperscaler capex

OEM backlog and hyperscaler capex are joined at the source. Post 067 documents the Siemens Energy CFO commentary attributing US demand explicitly to data centers, the clearest OEM-side acknowledgment of the hyperscaler-OEM coupling.

05.25

Siemens Energy Q2 FY26: €154B Backlog, Guidance Raised

Siemens Energy's Q2 FY2026 print on May 12 booked another €17.7B in all-time-record orders, with Gas Services alone delivering €8.9B and 77 turbine orders (12 GW). Order backlog reached €154B; FY26 guidance was raised to 14-16% revenue growth and ~€4B net income.

05.25

Hyperscaler Q1 2026 Capex: From $630B to $725B in One Quarter

The four hyperscalers reported Q1 2026 on April 29 and collectively raised 2026 capex guidance from the pre-quarter $630B figure to roughly $725B - up 77% from 2025's $410B. Microsoft alone now plans $190B, with $25B of that attributed to memory chip and component costs.

05.25

GE Vernova Q1 2026: Backlog Hits 100 GW, Orders +71%

GE Vernova's Q1 2026 print on April 22 turned the pre-guide into audited numbers: gas turbine backlog jumped from 83 GW to 100 GW in a single quarter, total backlog hit $163B, and the company pulled its $200B backlog target forward from 2028 to 2027. Pricing is rising faster than inflation.

05.25

The Order Book Hits the Tape

The AI power buildout has moved from forecast to order book. The richest companies in the world are prepared to spend almost without limit. They have discovered that money cannot manufacture time.